LKPI P102
DESCRIPTION
|
Description
|
Percentage of urgent repairs completed within time limits, as defined by the Right to Repair Regulations 1994 (Former BVPI 72). PFI1 and PFI2 data is not included.
|
|
Purpose/aim
|
This indictor monitors the efficiency of HFI and its contractors in meeting urgent repairs.
|
|
Definition
|
Urgent” is an arrangement to respond and complete repairs ranging from 1 to 7 working days. The Right to Repair Regulation 1994 sets out the list of defects and the prescribed period (in working days) for which the organisation must comply. The indicator asks for the number of urgent repairs completed by the authority as a percentage of all urgent repairs that could have been completed.
|
|
Formula
|
The denominator is: the number of urgent repairs that need access to the property. The numerator is: The number of urgent repairs completed by the authority.
|
|
Measurement period
|
Reported monthly through reporting year 1 April – 31 March
|
PROCEDURE FOR REPORTING
•
Purpose This is the procedure for reporting information on P100.
•
Scope The procedure applies to all information regarding P100 that is provided to HFI performance monitoring team, as defined on the PI record card.
•
Responsibilities Performance monitoring officer Matt Parsons is responsible for this procedure.
•
Responsibilities During Absence Performance officer Anne Mushington is responsible for this procedure.
PERFORMANCE INDICATOR RECORD
| Reference / Title | P100 – Percentage of urgent repairs completed within time limits, as defined by the Right to Repair Regulations 1994 |
| Link to Service Delivery Plan | |
| Departmental Responsibility | Kier Islington & Repairs Coordination Unit |
| Data Collector | |
| Performance Monitoring Officer | Matt Parsons |
| Method of Calculation | Proportion of all urgent repairs completed within timescale |
| Scope | All day to day repairs categorized |
| Collection frequency | Monthly |
| Record sheet | HMT data sheets / 12 Repairs / RTR CPA/ Monthly PI Recon. Checklist.xls |
| Where reported | HFI Property Services, SMT/HFI Board and Managed Property Sub Board |
| Current target | 95.0% |
| Result for 2007/08 | 94.3% |
| Current London top quartile | 97.77% |
| Current national top quartile | 98.68% |
| Benchmarks | HouseMark? |
| Date of last review | N/A |
| Other related indicators | |
This topic: Sandbox
> TestTopic44497 >
PropertyServices > LKPIP102
Topic revision:
25 Feb 2010, MattParsons
The copyright of the content on this website is held by the contributing authors, except where stated elsewhere. see CopyrightStatement. 